The German Online Access Act, as amended by the OZG-Änderungsgesetz in force since 24 July 2024, requires federal, state and local government to offer administrative services for businesses fully online by 2028 at the latest — end to end, so including the processing behind them. The duty to keep files electronically is not in that Act at all: for federal authorities it sits in § 6a of the E-Government Act, and even there as a "should" rule, while for municipalities it follows each state's own e-government law. Anyone putting a new document management system out to tender has to keep both in view, and write a set of specific requirements into the specification that were not mandatory five years ago.
This checklist sums up what must not be missing from an OZG-2.0-compliant DMS tender in 2026. It does not replace advice on German procurement law, but it arranges the requirements so that the usual traps are easier to avoid.
1. Sovereignty as a knock-out criterion
Hosting in Germany or the EU. The usual wording by now is "exclusively in German data centres". Use the word "exclusively" explicitly, otherwise your evaluation ends up including solutions that host "also" in the EU, but primarily somewhere else.
The full chain of sub-processors, documented. Ask for a list of ALL sub-processors, not just "Microsoft Azure" but also its CDN provider, mail provider and monitoring tools. More than five sub-processors should give you pause.
No CLOUD Act exposure. A vendor with a US parent company, even one trading as a German GmbH, can be obliged under the US CLOUD Act to hand data over. If that matters for your award decision, exclude US ownership in writing.
An EU data location contractually AND technically. A contractual promise is not enough on its own. Ask for technical evidence: data centre addresses, sub-processor audits.
2. Technical standards
The federal e-file standards. The binding XÖV standard for exchanging files, cases and documents between German public bodies is called xdomea. It is maintained by KoSIT, the coordination office for IT standards, and was adopted by the IT Planning Council. Ask for xdomea 4.0.0. That is the floor, not the ceiling: versions 3.0.0 and 3.1.0 expired on 31 August 2026 according to the XRepository, the official German standards registry, so a specification that still asks for 3.x is asking for a withdrawn version. A note for whoever writes the specification: there is no standard called "XAkte", even though the name turns up in tender documents — a bidder cannot cleanly meet a requirement written that way.
A FIT-Connect interface. FIT-Connect carries a citizen's request from the online portal into the right case file. From 2026 it is mandatory in many federal states.
A FIM master-data interface. FIM, the federal information management scheme, supplies the data that pre-fills application forms.
Conformity with a filing plan. The KGSt filing plan, and optionally your own or a municipality-specific one. File reference numbers have to be issued automatically, following defined rules.
OpenDesk compatibility. If you want to move to the federal sovereign workplace in the longer run, check whether the DMS vendor has a connector to OpenDesk, or plans one.
3. Data protection and IT security
Oriented towards the BSI baseline protection. Architecture and operation should follow the BSI baseline protection profile for municipal administration. Full certification of a DMS product itself is rare. What matters is that it fits cleanly into your information security management system.
ISO 27001 for the hosting. Even where the DMS itself holds no certificate, the hosting setup has to be ISO 27001 certified. The certificate belongs to the data centre operator, not to the software, so ask for it at that level. Hetzner, STACKIT, plusserver and IONOS meet it in the relevant tariffs.
Encryption in transit (TLS 1.3) and at rest (AES-256). Both mandatory, not optional.
Two-factor authentication. Mandatory for every administrative account, and strongly recommended for everyone with access to personal data.
A complete audit trail. Every access to every file has to be logged, with user, timestamp and action. Exportable in a format a supervisory authority can read.
4. Procurement-law aspects
Lots that smaller suppliers can bid for. Rather than a five-year all-in contract with a hyperscaler, use smaller lots: licences, hosting, consultancy and training kept apart. That allows more competition and reduces lock-in.
A data-export clause. Settle in the contract which format a full export comes in and how long it may take at the end of the contract. Ideally at no charge.
A right to source-code escrow. If the vendor becomes insolvent you need to be able to take delivery of the code. That matters for administrative files you cannot simply abandon.
A cap on annual price increases. For example "no more than the consumer price index plus two per cent". It protects you against opportunistic rises.
A minimum term, then notice month by month. Twelve to thirty-six months is usual, after that monthly. Agree to a longer term only if the price is clearly better for it.
5. Evaluating the bids
If you want to use a sovereignty matrix as your scoring grid instead of simply price times function, this is a workable structure:
- Data location (10-15 % weighting)
- Source-code availability and open source (5-10 %)
- Standardised data formats (5 %)
- Interface standards (5-10 %)
- Vendor independence and the sub-processor chain (10 %)
- Smaller supplier rather than hyperscaler (5 % as a boost for mid-sized vendors)
- Function (30-40 %)
- Price (15-20 %)
- Quality of implementation and support (10 %)
A weighting like this favours small vendors with a short sub-processor chain, such as Aktenplatz for the public sector, even where their feature range is narrower than that of the large suites. That is the point of the grid: it prices in what a wide feature list does not show.
6. What many people underestimate
How long implementation takes. For an OZG-relevant DMS setup, four to eight weeks is fast and six to twelve months is realistic. Tender in 2026 and you are usually live in 2027.
The training effort. Case workers need one to two days of training, power users three to five. If that is not in the contract, it arrives later as an extra cost.
The migration effort. Migrating from an older DMS is often a separate project with its own budget. Settle the question of format compatibility before you start.
The running cost of updates. Some DMS vendors bill the licence and the maintenance separately, and the maintenance is charged as a share of the licence cost every year. Ask for that share as a figure, because together the two are the real running cost.
In closing
An OZG-2.0-compliant DMS tender in 2026 is not a routine procurement. The requirements around sovereignty, data protection and technical standards are specific enough that many standard tender documents fail on them.
This checklist covers the main points. It does not replace being accompanied through the procurement by someone experienced in German public tendering. If you have a concrete question about your own tender, talk to us. We advise on the specification free of charge, including in cases where Aktenplatz does not end up winning the award.